CPS Westover Hills

138kV Switchgear & Transformer Addition

This project was a 138kV bus and high-voltage equipment expansion. The work involved dress out and processing two new transformers, pulling and terminating control cable in two new switch gear units, moving complete dead-end structure in one piece to new location, and installing new high-voltage switches and aluminum bus extension.

E.P. Breaux Utility Services provided complete above grade construction services and material management.